Our fifteenth week was spent finalizing our two installations for the BVW Festival. We had successfully showcased our M_rror installation at the Dirty Ball on…
On Monday our team presented our two pieces to the faculty for our penultimate milestone “Soft Opening.” We demonstrated how the pieces work technically, and…
We went into full crunch this week as pushed toward our Soft Opening and we’ve been busy! First and foremost, we developed an artistic identity…
Time is ticking down! We are now just one week away from “Soft Opening” which is our penultimate milestone before the end of the semester….
Phew, what a week. After bouncing back from GDC, we came into our project room, and it was like christmas morning! So many packages! We…
Our parts arrived! It was a relief to see all of the boxes when we had returned from San Francisco. We spent some time on…
We presented our project on Monday (3/18) for our Halves milestone! We were very excited to share our progress throughout the first part of the…
Last week, we came up with the idea of creating a set of mirrors that react to a guest’s presence by turning away from them…
After the success last week of our “Mirrors” idea, we repeated the same week-long process. On Monday we brought new ideas to the table and…
With the team renewed with energy, we plunged into a week-long exploration of a different concept. We spent time individually brainstorming concepts, ranging from fully-formed…